Timeline
- Apr. 2017Ground Breaking Ceremony in Sainshand with the provincial government
- Oct. 2016Start of preparatory works for construction
- Sep. 2016United Green comes on board as co-developer
- Jul. 2015Power Purchase Agreement and Dispatch Agreement signed
- Dec. 2014Tariff approval by the Energy Regulatory Commission (ERC)
- Mar. 2014Construction license
- Dec. 2013Land permission on city level
- Oct. 2013Environmental Impact Assessment approved by the Ministry of Environment and Urban Development
- Sep. 2013Project approval by the Technical & Science Committee of the Ministry of Energy and preparation of grid capacity study by the NDC
- May. 2013“Desert Solar Power One LLC” was established
- Apr. 2013Feasibility study for the most suitable project location
- Jan. 2013On-site investigation (German geologists and PV specialists) of seven potential project sites
- Dec. 2012Memorandum of Understanding with Ministry of Energy