Timeline

Timeline
  •  Apr. 2017Ground Breaking Ceremony in Sainshand with the provincial government
  •  Oct. 2016Start of preparatory works for construction
  •  Sep. 2016United Green comes on board as co-developer
  •  Jul. 2015Power Purchase Agreement and Dispatch Agreement signed
  •  Dec. 2014Tariff approval by the Energy Regulatory Commission (ERC)
  •  Mar. 2014Construction license
  •  Dec. 2013Land permission on city level
  •  Oct. 2013Environmental Impact Assessment approved by the Ministry of Environment and Urban Development
  •  Sep. 2013Project approval by the Technical & Science Committee of the Ministry of Energy and preparation of grid capacity study by the NDC
  •  May. 2013“Desert Solar Power One LLC” was established
  •  Apr. 2013Feasibility study for the most suitable project location
  •  Jan. 2013On-site investigation (German geologists and PV specialists) of seven potential project sites
  •  Dec. 2012Memorandum of Understanding with Ministry of Energy